A manufacturing facility needed to improve access and functionality within its loading dock area by adding a new roll-up door opening to an existing CMU wall. Because the modification involved altering an existing structural wall, the project required structural engineering to safely accommodate the new opening and provide the necessary steel framing.
Chief Engineering was brought in to evaluate the existing conditions and develop a structural solution for the new roll-up door. The design needed to account for the existing CMU wall while providing a new steel framing system capable of supporting the opening. The scope included field verification, design of the header beam and jamb posts, development of the anchorage system, and preparation of Issued for Construction (IFC) drawings.
Chief Engineering developed the structural design for the new roll-up door opening and documented the required steel framing and connections for construction. The project required coordination between structural calculations, existing site conditions, and the contractor-driven nature of the work to provide a practical solution that could be implemented in the field.
The project reinforced the importance of assigning the appropriate resources and maintaining clear communication and documentation throughout the design process. It also highlighted that roll-up door modifications are often highly contractor-driven, requiring significant calculation and coordination. For similar projects, Chief found that supporting the contractor as a structural engineering resource can be more effective than taking the lead on the work.
Despite the challenges, the client was pleased with Chief Engineering’s work and subsequently requested another project bid, demonstrating continued confidence in the firm’s ability to support its ongoing engineering needs.